The project involves the remediation of a leaking 10-inch medium pressure bolted flange, which has been exposed following excavation. This
flange is positioned in close proximity to a heavily trafficked motorway junction, where significant ground movement and vibration are common
place. The current issue involves a leakage occurring at a pressure of 27 psi, necessitating urgent attention to prevent further environmental
impact and potential operational disruptions.
Previous efforts to address the leak using anaerobic sealing products from another supplier have not achieved the desired results, prompting
the need for a thorough reassessment and effective remedial action. Given the critical location and the nature of the leak, a robust solution is
imperative to ensure the integrity and reliability of the flange system under operational conditions affected by continuous ground dynamics
and vehicular vibrations.